譽耐PC陽光板(耐力板)的施工工藝
1、彈線:依據圖(tu)紙的標高及(ji)陽(yang)光板頂棚(peng)方(fang)位尺度(du)和已測定的中心線,彈出中空板頂棚(peng)主骨架(jia)方(fang)位線。
2、預(yu)埋件:依據標高控制線(xian)中(zhong)空板(ban)頂棚主(zhu)骨架(jia)(jia)方(fang)位(wei),查(cha)看(kan)洞口反(fan)梁(liang)上(shang)外(wai)表標高是否符合規劃(hua)要求,如有(you)差異應剔鑿或用高強度等(deng)級(ji)水泥砂(sha)漿找平處理,到達(da)強度后,按深(shen)化規劃(hua)節點詳圖預(yu)埋鋼(gang)(gang)板(ban)尺(chi)度放出膨脹(zhang)螺栓方(fang)位(wei)線(xian),然(ran)后鉆孔(kong)安放膨脹(zhang)螺栓,裝置(zhi)鋼(gang)(gang)板(ban)與脹(zhang)栓固定。再將主(zhu)骨架(jia)(jia)中(zhong)心線(xian)投(tou)至預(yu)埋鋼(gang)(gang)板(ban)上(shang)。
3、譽耐中(zhong)(zhong)空(kong)板(ban)裝(zhuang)置主(zhu)骨(gu)架:依據彈(dan)出中(zhong)(zhong)空(kong)板(ban)頂棚主(zhu)骨(gu)架方位(wei)線(xian)(xian),先裝(zhuang)置兩頭(tou)后(hou)(hou)中(zhong)(zhong)心有(you)些(xie),其方法(fa):將60mm×60mm×3mm方鋼管(鍍鋅)主(zhu)骨(gu)架在(zai)屋面上組裝(zhuang)好后(hou)(hou),用人(ren)力安放在(zai)方位(wei)線(xian)(xian)上,用線(xian)(xian)墜吊垂直面,中(zhong)(zhong)心暫時固(gu)定后(hou)(hou)與預埋(mai)鋼板(ban)進行焊接。兩頭(tou)主(zhu)骨(gu)架安好后(hou)(hou),拉中(zhong)(zhong)心和(he)兩邊(bian)各(ge)1500mm高度(du)(從鋼板(ban)兩頭(tou)支座往上量)三條縱向通線(xian)(xian)后(hou)(hou),再從一端向另一端逐一裝(zhuang)置至(zhi)全部完結。
4、裝(zhuang)置(zhi)(zhi)次骨(gu)架:在譽耐中(zhong)空板頂棚主(zhu)骨(gu)架裝(zhuang)置(zhi)(zhi)固(gu)定(ding)完畢后,裝(zhuang)置(zhi)(zhi)中(zhong)空板頂棚60mm×60mm×3mm方鋼次骨(gu)架,并調準(zhun)方位,調平(ping)后,與主(zhu)骨(gu)架焊接固(gu)定(ding)。在裝(zhuang)置(zhi)(zhi)中(zhong)空板的一起(qi),安(an)放防潮(chao)劑。
5、裝(zhuang)置外層(ceng)譽耐(nai)中空板(ban):依照深化規劃排(pai)版(ban)方(fang)位,將(jiang)準備(bei)好尺度適宜的(de)外層(ceng)20mm厚的(de)譽耐(nai)陽光板(ban)進行(xing)裝(zhuang)置裝(zhuang)